Laura Speed Elliott Middle School had significant student safety and building needs that required a roof replacement.
As of October 2020:
- The roof replacement at LSE Middle School is complete.
- Tuckpointing/lintels/windows are complete.
- Science room remodels and some rooms sizes were adjusted.
The next phase:
- Sidewalk repair is anticipated in December 2020.
- Ongoing HVAC repairs.
- Lockers/flooring/casework (estimated completion 8/21.)
As of December 2020:
- Cooling tower has been replaced.
- Sidewalk repairs are planned for spring 2021.
As of March 2020:
- Sidewalk repairs have begun.